First HM-7 Test Fire Scheduled

After a very successful dry run of the motor test fire last Saturday, we are prepared to do it for real this Saturday (2/20)! Set up will begin on Friday (2/19) at about 3:30 p.m. We will be taking the trailer down to the prop lab and laying out some cable. Electronics set up will begin Saturday morning at about 9:00 AM.

The maximum occupancy for the control room is 10, limited to those conducting the test. We will have a livestream that will be viewable in the Aero Conference room (41-112) near the propulsion lab. The livestream will be available on YouTube, and will have views both of the motor and the control room.

An email will be sent out with the livestream link and the YouTube playlist on the Media page will be updated.